Safety Evaluations with Open Items for Calvert Cliffs, Unit 3 Application

The following table provides access to Final Safety Evaluations that the NRC has issued in connection with its review of the COL application that Calvert Cliffs 3 Nuclear Project, LLC and UniStar Nuclear Operating Services, LLC submitted for Calvert Cliffs, Unit 3.

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

Chapter Description Date
1 Introduction and General Description of Plant TBD
2 Site Characteristics - Sections 2.0 through 2.3 10/29/10
Hydrologic Engineering - Section 2.4 10/23/13
Geology, Seismology & Geotechnical Engineering - Section 2.5 04/12/13
3 Design of Structures, Components, Equipment, and Systems (Except Section 3.7) 01/25/13
4 Reactor 03/24/10
5 Reactor Coolant System and Connected Systems 03/30/10
6 Engineered Safety Features 04/01/11
7 Instrumentation and Controls Systems 10/17/11
8 Electric Power 01/20/10
9 Auxiliary Systems 10/08/13
10 Steam and Power Conversion System 06/16/10
11 Radioactive Waste Management 10/21/10
12 Radiation Protection 03/18/10
13 Conduct of Operations 05/02/13
14 Initial Test Program 01/24/13
15 Accident and Analysis 07/22/11
16 Technical Specifications 11/04/10
17 Quality Assurance 04/29/10
18 Human Factors Engineering 10/31/11
19 Response to Severe Accident Policy Statement 04/30/10