Combined License Application Documents for Aurora – Oklo Power Plant Application
The following table provides access to the COL Application and other documents that Oklo, Power LLC submitted for Aurora – Oklo Nuclear Power Plant.
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.
Date | Description | Status |
---|---|---|
1/06/2022 | OKLO INC. - Denial of the Aurora Combined Operating License Application for Failure to Supply Information | No further action |
1/06/2022 | Completeness Determination of Oklo-2021-R19-NP, Revision 3, "Maximum Credible Accident Methodology," and Oklo-2021-R20-NP, Revision 1, "Performance-Based Licensing Methodology" | No further action |
10/19/21 | Oklo Inc., Submittal of Performance-Based Licensing Methodology Rev. 1 | Completeness Determination: Submittal of Performance-Based Licensing Methodology Rev. 1 1/06/2022 |
10/05/21 | Oklo Inc. – Submittal of Maximum Credible Accident Methodology Rev. 3 | Completeness Determination: Submittal of Maximum Credible Accident Methodology Rev. 3 1/06/2022 |
09/02/21 | Oklo, Inc. Fee Waiver Response Letter | No further action |
08/05/21 | Oklo Performance-Based Licensing Methodology Topical Report Completeness Determination | Oklo Response 10/19/2021 |
08/05/21 | Oklo Maximum Credible Accident Topical Report Completeness Determination | Oklo Response 10/05/2021 |
07/02/21 | Oklo, Inc. – Submittal of Maximum Credible Accident Methodology Topical Report and Performance-Based Licensing Methodology Topical Report | Completeness Determinations: Maximum Credible Accident 8/05/2021 Performance-Based Licensing 8/05/2021 |
06/17/21 | Oklo, Inc. – Letter of Intent Fee Waiver Request for Review of Maximum Credible Accident Methodology Topical Report and Performance-Based Licensing Methodology Topical Report | Review completed NRC response letter to Oklo 09/02/2021 |
12/23/20 | Oklo Aurora – Step 1 Review Regulatory Applicability Audit Summary (EPID L-2020-NEW-0004) | Audit Plan 09/28/20 |
12/21/20 | Oklo Inc. Response Letter to the NRC Letter, Oklo Power LLC Extension of Step 1 Technical Review of Key Safety and Design Aspects of the Aurora Powerhouse, November 17, 2020 | Oklo Response to NRC 11/17/20 Step 1 extension letter |
12/21/20 | Oklo Inc. Response Letter to the NRC Letter, Oklo Step 1 Technical Review of Key Safety and Design Aspect Activities Related to the Applicability of Regulations, November 17, 2020 | Oklo Response to NRC 11/17/20 Applicability of Regulations letter |
11/17/20 | Oklo Power LLC Extension of Step 1 Technical Review of Key Safety and Design Aspects of the Aurora Powerhouse | NRC Letter to Oklo extending Step 1 review |
11/17/20 | Oklo Step 1 Technical Review of Key Safety and Design Aspect Activities Related to the Applicability of Regulations | NRC Letter to Oklo on the Applicability of Regulations to the Aurora design |
10/30/20 | RAI Responses Step 1 Aurora Oklo | Oklo RAI response package |
10/01/20 | Step 1 Structures, Systems, and Components Classification Request for Additional Information Audit Plan | Audit Summary not issued to date |
09/28/20 | Regulatory Applicability Audit Plan – Oklo Aurora | Audit Summary 12/23/2020 |
09/23/20 | Request for Additional Information – Aurora Reactor Step 1 – Review Safety Classification of Systems, Structures and Components | RAI Responses 10/30/20 |
09/22/20 | Step 1 Maximum Credible Accident Request for Additional Information Audit Plan | Audit Summary not issued to date |
09/21/20 | Request for Additional Information – Aurora Reactor Step 1 – Review, Maximum Credible Accident – Heat Transfer in the Reactor System | RAI Responses 10/30/20 |
09/18/20 | Request for Additional Information – Aurora Reactor Step 1 – Review, Maximum Credible Accident | RAI Responses 10/30/20 |
09/18/20 | Request for Additional Information – Aurora Reactor Quality Assurance Program | RAI Responses 10/30/20 |
09/18/20 | Summary of Audit for the Oklo Power LLC Aurora Reactor Step 1 – Review, Maximum Credible Accident – Heat Transfer in the Reactor System | Audit Plan 08/13/20 |
08/19/20 | Summary of Audit for the Oklo Power LLC Aurora Combined License Application Acceptance Review | Audit Plan 04/01/20 |
08/13/20 | Audit Plan for the Oklo Power LLC. Aurora Reactor Step 1 – Review, Maximum Credible Accident – Heat Transfer in the Reactor System | RAIs 09/21/20 RAI Responses 10/30/20 Audit Summary 09/18/20 |
06/24/20 | Aurora Oklo – FRN Notice of Hearing and Opportunity for leave to Intervene | 7/31/20 – 12/22/20 Emergency Petition Beyond Nuclear, et. al. Package includes petition, and responses from NRC staff, Oklo, and NRC Commission |
06/05/20 | Acceptance Review for the Oklo Aurora Combined License Application | Acceptance review letter describes Step 1 and Step 2 review. |
04/01/20 | Audit Plan for the Oklo Power Aurora Reactor Combined License Application Acceptance Review | Audit Summary 08/19/20 |
03/11/20 | Oklo Power Combined Operating License Application for the Aurora at INL | Application submittal package Accepted for Review 06/05/20 |
Page Last Reviewed/Updated Saturday, September 17, 2022
Page Last Reviewed/Updated Saturday, September 17, 2022