Skip to main content

Alert

The NRC is shutdown due to the lapse in appropriations. Exempted activities to maintain critical health and safety activities and progress on critical activities, including activities outlined in Executive Order 14300, as described in the OMB Approved NRC Lapse Plan will continue.

§ 52.85 Administrative review of applications; hearings.

A proceeding on a combined license is subject to all applicable procedural requirements contained in 10 CFR part 2, including the requirements for docketing (§ 2.101 of this chapter) and issuance of a notice of hearing (§ 2.104 of this chapter). If an applicant requests a Commission finding on certain ITAAC with the issuance of the combined license, then those ITAAC will be identified in the notice of hearing. All hearings on combined licenses are governed by the procedures contained in 10 CFR part 2.

[72 FR 49534, Aug. 28, 2007]

Page Last Reviewed/Updated Wednesday, March 24, 2021